COMPLEX LEBÁRIO - ESPANHA

The activities developed in this work began in 2011 and Final lasted until 2013.
The activities undertaken by ASR Ltd, this work began in 2011 and Final lasted until 2013.
The main activities were:
  • Running bases reinforced concrete pavement with application of mesh sun;
  • Settlement of paving flags based on hydraulic rigging;
  • Laying concrete curbs and garden tours;
  • Grooving concrete drainage, performed "in situ";
  • Placement of drainage channels and cast iron sinks;
  • Execution coating steps with prefabricated "American type";
  • Support services building.